So that the cycle time optimalization is efficient, some of the IMM adjustment parameters must be
checked or modified :
the Partial Opening position (OPA) must be adjusted to authorise the robot arms
descent as soon as possible (avoiding any risks of collision)
the IMM movement speeds and accelerations (mould, ejectors and core pullers) must
be optimised to a maximum, whilst at the same time respecting the quality of the parts
produced and the safety of the equipment.
if possible, the fastest movements must be respected : for example, if the mould opening
is quicker than the part ejection, the cycle time will be less penalised if the opening
is large enough to mask the ejectors and/or core pullers back and forward time during
the robot movements.
Reminder : the equipments productivity is calculated over long production periods. Consequently, stops
due to incidents are taken into account.
An efficient cycle time optimalization MUST :
Reduce the part fabrication time
An efficient cycle time optimalization MUST NOT :
Increase the number of reject parts
Increase the number of incidents
Sepro proposes, as an option, an additional means of cycle time optimalization : anticipated restart that
enables you to mask the IMM reaction time (see chapter V 5. page 64).